A bridge replacement project on KY 330 (Falmouth-Morgan Road) in Pendleton County will begin construction the week of Aug. 15.

KY330_EB_Aug2016Rob Hans, chief district engineer for KYTC District 6 said, “The new bridge and approaches will be constructed to current standards that will provide better mobility for the motorists who travel this roadway.”

The new bridge will be 183-feet long with two 12-foot lanes and 4-foot shoulders.   The bridge will be elevated higher than the current structure to improve safety.

The current bridge will remain in place while the new span is being constructed.

Drivers should be cautious when entering the construction zone.

Frederick & May Construction Co., of West Liberty was awarded the low bid contract for $1.78 million. The anticipated completion is May of 2017.